While installing the new sewer mains, crews have also been installing new water mains while the road is already trenched. It is now the time in the project to swap water customers’ service lines from the old water main to the new water main.
This will require a brief, overnight disruption of water service for each water customer within the sewer district on Great Road and King Street. This work is scheduled for September 23 through November 30 and possibly later until work ceases for the winter, but is subject to change at the contractor’s discretion and due to weather. This schedule has been updated from the original completion estimate of November 15.